Virginia’s hearing on the proposed Dominion Energy–NextEra Energy merger continued Friday, Nov. 20, with cross-examination of State Corporation Commission staff witnesses, VPM reported from the proceedings. The case concerns whether NextEra should be allowed to take control of Dominion Energy Virginia as part of the merger. Staff and the companies disagree over which protections the Virginia utility would need under a new parent. The commissioners have yet to decide. [1] [2] [3]
Where the companies and staff differ
Commission staff have called for a majority of independent directors on the Virginia utility’s board and a ten-year commitment on Virginia staffing. The companies’ rebuttal filing proposed adding two independent directors to a five-member board and maintaining a Virginia employee headcount floor for five years after closing. The companies argue their proposals would protect the utility while allowing it to benefit from the parent company’s capital and expertise. VPM reported that staff’s lawyer told commissioners that staff opposed approval without additional safeguards. [1] [3]
What Virginia law requires
Under Virginia’s Utility Transfers Act, the commission must be satisfied before approving the transfer that adequate public service at just and reasonable rates will be protected. The law allows commissioners to make approval subject to conditions. For customers, the board and staffing disputes concern how the Virginia utility would be run after a change in ownership and what obligations the commission could enforce. VPM reported that the companies argued their greater size would help contain costs. Those projected benefits remain part of the companies’ case. [1] [3] [4]
What happens after Friday’s hearing
The evidentiary hearing began Nov. 17. The commission’s case page shows proceedings continuing Monday, Nov. 23, and links to the webcast. VPM reported that additional testimony, cross-examination and rebuttal would continue into Tuesday. The commission’s review remains open under case number PUR-2026-00112. Its decision will determine whether the companies can proceed with the Virginia transfer and what conditions would attach to any approval. [1] [2] [4]