A new archival essay by the Oregon planner who writes as Bryan at Low Velocity revisits how Enchanted Forest, the family-run theme park near Turner, sought room to expand. The Nov. 22 essay traces a 2018 application through Marion County’s 2019 hearings. County records show that the case turned on both the uses a rural commercial zone would allow and how the park would meet neighboring properties. [1] [2] [3]
What the family asked the county to change
Tofte Family LLC sought to move 7.15 acres of an adjoining property from acreage residential to commercial zoning, amend the county’s comprehensive plan designation and shift the property line. The hearings officer described the parcel as a possible extension of the existing amusement park. The application asked the county to change what the land could be used for, with development proposed for the future. [2]
Why the choice of zone mattered
The hearings officer’s report says the county had already rezoned the park in 1985 and limited which commercial uses it could host. By 2019, that older commercial zone had been replaced. The hearings officer found that the current rural commercial zone allowed amusement and recreation but also allowed uses such as warehousing or auto wholesaling. A limited-use overlay could narrow those options for this parcel. A July submission from the applicant argued that the newer zone’s existing restrictions made a separate overlay unnecessary. [2] [3]
What commissioners recorded in July
The July 17 draft minutes record a unanimous motion accepting the hearings officer’s recommendations with a 20-foot setback, a maintained natural vegetation buffer and a prohibition on public access via Hanneman Lane. The Oct. 16 agenda then listed an ordinance granting the application for consideration. The July minutes record the vote on the recommendations, while the October agenda establishes that the ordinance was scheduled for consideration. [4] [5]