SDG&E shifts preferred power line route from Temecula to South Mountain

Temecula remains on an alternate route for the Golden Pacific Powerlink. California regulators list the project in pre-filing consultation.

San Diego Gas & Electric has switched its preferred route for the Golden Pacific Powerlink from the Riverside County corridor through Temecula to the South Mountain corridor. The utility confirmed the change in a statement published Nov. 20 by Save Temecula, a group opposing the project. The previous corridor remains among the alternatives on SDG&E’s project map. [1] [2]

What changed on the map

South Mountain had appeared as an alternative in earlier project materials. SDG&E’s updated map identifies that corridor as proposed and shows the Riverside County route as an alternative, alongside the Imperial West and Montezuma Grade alternatives. The shift changes which communities are near the proposed route. The utility said its studies and feedback suggested the switch could reduce some environmental effects and ease engineering challenges, and said it would continue studying the new route’s potential impacts. [1] [2] [3] [4]

Why Temecula remains in the discussion

Save Temecula credited residents who spoke up and said it would continue opposing the project. The group pointed to the city’s continued inclusion on the alternatives map and raised concerns about possible wildfire risk from the preferred corridor. SDG&E described the maps as preliminary. The California Public Utilities Commission says its environmental review will draw on project materials and information from the public, Tribes and other agencies. [1] [2] [5]

What California regulators will review

The project would connect the existing Imperial Valley Substation to a new substation in Orange County via a roughly 150-mile, 500-kilovolt transmission line, according to the commission. The commission’s current-projects list places it in pre-filing consultation. Once an application is complete, the CPUC says it will conduct an environmental review and a separate formal proceeding to determine whether the project is needed and in the public interest. Its project page describes opportunities for public comments once those proceedings begin. [5] [6]

Beyond the headline

The conversation

Bluesky
“SDG&E’s new preferred route for the Golden Pacific Powerlink transmission line passes through Anza-Borrego Desert State Park and the Cleveland National Forest”

Fire historian Jared Dahl Aldern describes his reading of a preliminary route map.

Read on Wildroot
Read more on this topicExplore on Wildroot

Sources & documents

Follow the numbered references to the reporting and original records.

  1. Nov. 20 SDG&E route statement published by Save Temeculasavetemecula.org
  2. SDG&E’s Golden Pacific Powerlink project and alternativesgoldenpacificpowerlink.com
  3. SDG&E’s current route overview maphdp-us-prod-app-wspusa-goldenpacific-files.s3.us-west-2.amazonaws.com
  4. City of Temecula’s earlier South Mountain alternative map and briefingtemeculaca.gov
  5. CPUC Golden Pacific Powerlink project and review processia.cpuc.ca.gov
  6. CPUC current permitting and environmental review projectscpuc.ca.gov