The GEO Group expects to complete activation of four immigration detention facilities by the end of March 2027 or earlier, ahead of the Department of Homeland Security’s estimated August 31 completion date for a broader detention expansion plan or similar document. Both timetables could change. [1][2]
In its November 5 earnings release, GEO forecast that activation of Big Horn in Colorado and Rivers in North Carolina would be completed by the end of 2026, and the two-facility Big Spring complex in Texas by the end of March 2027. Their combined stated capacity is 4,837 beds, not a count of detainees or net national growth. [1]
If both schedules hold, those activation milestones would precede the plan’s estimated completion by about eight and five months, respectively. Activation does not establish actual operation, and the records do not establish a legal requirement to finish the plan first. [1][2]
In its September report, the Government Accountability Office said U.S. Immigration and Customs Enforcement (ICE) pursued expansion without a comprehensive strategic plan and recommended one covering goals, activities and resources. DHS agreed, saying its document would also address milestones, capacity, staffing, funding and coordination. GAO said faster completion might be warranted given the spending and potential waste; its findings do not establish a deficiency at these facilities. [2]
Congress appropriated $45 billion in 2025 for single-adult detention and family residential capacity, available through September 30, 2029. GAO says the multi-year detention funding is subject to apportionment based on approved annual spending plans. The records do not show the amount remaining or how these facilities are funded. [2][3]